Sarawak Pan Borneo Highway Project: Sibuti Section Ramps Up Pipe Relocation Work
Overview of the Project
The Sarawak Pan Borneo Highway project is a massive infrastructure development initiative that aims to connect the eastern and western parts of Sarawak, a state in East Malaysia. The project involves the construction of a 786-kilometer highway, divided into 25 sections, with 11 contractors appointed to carry out the work. The project is expected to be completed in 2026.
Current Progress
According to Deputy Prime Minister Datuk Seri Fadillah Yusof, the Sibuti section in Miri is one of the last areas still under construction before the highway is fully completed. Currently, pipe relocation work is being carried out in this section, which has caused a delay in the project’s progress.
Challenges and Expectations
Fadillah Yusof emphasized that the pipe relocation work is a crucial step in the construction process, and construction work cannot proceed until the new pipes are completed. He assured that the project is not yet fully completed, but he expects it to be ready by 2026.
Previous Reports
Deputy Works Minister Datuk Seri Ahmad Maslan was previously reported to have said that the Sarawak Pan Borneo Highway project had reached 99 per cent completion as of July last year. However, the current delay in the Sibuti section has affected the overall progress of the project.
Contract Packages and Contractors
The Sarawak Pan Borneo Highway project is divided into 11 contract packages, each involving different sections of the highway. Eleven contractors have been appointed to carry out the work, which is expected to be completed in 2026.
Conclusion
The Sarawak Pan Borneo Highway project is a significant infrastructure development initiative that aims to connect the eastern and western parts of Sarawak. While the project is almost complete, the Sibuti section’s pipe relocation work has caused a delay. The project is expected to be fully completed by 2026, and its completion will have a significant impact on the state’s economy and connectivity.
FAQs
Q: What is the current status of the Sarawak Pan Borneo Highway project?
A: The project is almost complete, with the Sibuti section still under construction due to pipe relocation work.
Q: When is the project expected to be completed?
A: The project is expected to be fully completed by 2026.
Q: What is causing the delay in the Sibuti section?
A: Pipe relocation work is causing the delay in the Sibuti section.
Q: How many contractors are working on the project?
A: 11 contractors have been appointed to carry out the work.